Construction has been suspended at Google's data centre project in the Farciennes and Aiseau-Presles area near Charleroi following a halt order from Walloon authorities. The stoppage came after the company proceeded with building work for several months despite losing its permit to use water from the Sambre river for cooling systems. Greenpeace Belgium's intervention prompted the regional government to act, with the matter now headed to court in January.
When the order took effect on Thursday, approximately 300 construction workers were present at the site, according to Raphael Stokis, a Walloon official who spoke with Belgian broadcaster VRT. The infrastructure minister, François Desquesnes, had initiated an investigation the previous day.
Permit changes and revocation timeline
Google's initial permit, issued in 2024, authorized three data centres using air cooling technology. During 2025, the company modified its proposal by consolidating two structures into a single larger facility and switching to water-based cooling from the Sambre river, as documented by Greenpeace. The Walloon administration granted approval for these changes in April 2026.
Following resident objections, Desquesnes cancelled the amended permit in August. The proposed water withdrawal reached 600 cubic metres per hour, with less than a quarter scheduled to return to the river, according to Belga news agency. When residents subsequently reported ongoing construction activity, Greenpeace launched an investigation using satellite imagery and initiated emergency procedures earlier this week.
Tech giants are not above the law. This should already have been the case in August, when the permit was cancelled.
Nadia Cornejo, Greenpeace Belgium spokesperson
Legal proceedings and Google's response
Google filed an appeal challenging the permit revocation but proceeded with construction work without awaiting a court decision, VRT reported. On 17 October, the company petitioned Belgium's Council of State to overturn and suspend the minister's decision. Greenpeace and multiple residents submitted requests to participate in the proceedings on 16 November, with a public hearing scheduled for 7 January.
Google is committed to an open and collaborative dialogue with the regional government and experts on its investments in Wallonia.
Google spokesperson to VRT
Data centre projects have encountered comparable community resistance in other locations. A Google facility in Finland triggered a police investigation, while residents in Indonesia's Batam protested water usage concerns in October. American voters also rejected data centre proposals during midterm elections.